Table of Contents
2.......... Project Information
2.3 Construction Programme and
Activities
2.5 Status of Environmental Licences,
Notification and Permits
3.......... Environmental Monitoring
Requirements
3.1 Construction Dust Monitoring
3.2 Construction Noise Monitoring
4.......... Implementation
Status of Environmental Mitigation Measures
5.......... Monitoring
Results
5.1 Construction Dust Monitoring
5.2 Regular Construction Noise
Monitoring
6.......... ENVIRONMENTAL
SITE INSPECTION AND AUDIT
6.2 Summary of Monitoring Exceedances
6.3 Summary of Environmental
Non-Compliance
6.4 Summary of Environmental Complaints
6.5 Summary of Environmental Summon and
Successful Prosecutions
7.1 Construction Programme for the Next
Three Month
7.2 Key Issues for the Coming Month
7.3 Monitoring Schedule for the Coming
Month
8.......... ConclusionS AND
RECOMMENDATIONS
List of Tables
Table
2.1........... Construction Activities in the
reporting month
Table
2.2........... Contact
Information of Key Personnel
Table
2.3........... Status
of Environmental Licenses, Notifications and Permits
Table
3.1 ......... Air Quality Monitoring Equipment
Table
3.2 ......... Location of Construction Dust Monitoring Station
Table
3.3 ......... Noise Monitoring
Parameters, Frequency and Duration
Table
3.4 ......... Noise Monitoring Equipment for Regular Noise
Monitoring
Table
3.5 ......... Noise Monitoring Stations
during Construction Phase
Table
3.6 ......... Noise Monitoring
Parameters, Frequency and Duration
Table
4.1........... Status of Required Submission under
Environmental Permit
Table
5.1 ......... Summary of 24-hour TSP
Monitoring Result in the Reporting Period
Table
5.2 ......... Summary of 1-hour TSP
Monitoring Result in the Reporting Period
Table
5.3 ......... Summary of Construction
Noise Monitoring Results in the Reporting Period
Table
6.1 ......... Observations and
Recommendations of Site Audit
Table
7.1........... Construction Activities in the
coming three month
List of Figures
Site Layout Plan |
|
Location of Air Quality Monitoring Station |
|
Locations of Noise Monitoring Station |
List
of Appendices
Construction Programme |
|
Project Organization Structure |
|
Implementation Schedule of Environmental Mitigation Measures |
|
Summary of Action and Limit Levels |
|
Calibration Certificates of Equipment |
|
EM&A Monitoring Schedules |
|
Air Quality Monitoring Results and their Graphical Presentations |
|
Noise Monitoring Results and their Graphical Presentations |
|
Event and Action Plan |
|
Cumulative Statistics on Complaints, Notification of Summons and
Successful Prosecutions |
|
Monthly Summary Waste Flow Table |
Central Kowloon Route
– Kai Tak West (CKR-KTW; Contract No. HY/2014/07) (hereafter called “the
Project”) covers part of the construction of the Central Kowloon Route (CKR).
The Project comprises
the follow works:
·
50x30m
access shaft with noise enclosure at Ma Tau Kok
(MTK);
·
100m long
cut-and-cover (C&C) tunnel at MTK;
·
Demolition
and re-provisioning of MTK Public Pier;
·
160m long
underwater tunnel (UWT) (Stage 1);
·
210m long
UWT (Stage 2);
·
60m long
C&C tunnel at Kai Tak;
·
130m long depressed
road and 200m long underpass at Kai Tak;
·
390m long
underground tunnel ventilation adit at Kai Tak;
·
Seawall
demolition and construction of new landing steps; and
·
Barging
Point enclosure and conveyor system.
The EM&A programme commenced on 4 April 2018.The impact EM&A for the Project includes
air quality and noise monitoring.
This is the
nineteenth monthly EM&A Report presenting the EM&A works carried out
during the period between 1 and 31 October 2019. As informed by the Contractor, major activities in
the reporting period were:
Locations |
Site Activities |
Kai Tak |
·
Construction of ventilation adit, ·
Construction of at-grade road and associated backfilling
works, ·
ELS removal at ventilation adit, ·
Excavation works at Underpass, ·
Construction of New Right of Way, ·
ELS installation works, ·
Temporary Grouting |
Ma Tau Kok |
·
TTM implementation, ·
Soft Excavation and Rock Excavation, ·
Noise panel installation, ·
ELS installation & decking works for access shaft, ·
Construction of footpath, ·
Precast segment installation at Landing Step |
Kowloon Bay |
·
Wall tie installation and temporary reclamation for stage 1
temporary reclamation, ·
Preparation work of K-frame tower and sliding system, ·
Excavation for stage 1 underwater tunnel, ·
Temporary Grouting, ·
Seawall Removal |
Barging Point |
·
Barging point operation (Spoil Disposal) |
Breaches of Action and Limit Levels for Air Quality
All 24-hour TSP result was below the Action
and Limit Levels at all monitoring locations in the reporting month.
All 1-hour TSP result was below the Action and
Limit Levels at all monitoring locations in the reporting month.
Breaches of Action and Limit Levels for Noise
Regular Noise Monitoring
Six (6) noise related complaints were received in the reporting month. Based on the investigation result, the noise nuisance from the construction site was minimized with the proper implementation of mitigation measures. Therefore, six action level of noise was triggered and the investigation report was finalized on 14, 18, 24, 28 and 29 October 2019.
No
exceedance of Limit Level of noise was recorded in the reporting month.
Complaint, Notification of Summons and Successful Prosecution
Five
(5) complaints (received by 1823 on 27 September, 10, 16, 18 and 21 October
2019) were referred by the Contractor on 2, 14, 18, 21 and 24 October 2019, the
investigation report was finalized on 14, 18, 28 and 29 October 2019.
One
(1) complaint (received by Environmental Protection Department on 24 September,
2, 9 and 11 October 2019) were
referred by the Contractor on 17 October 2019, the investigation report was
finalized on 24 October 2019.
Reporting Changes
There was no
reporting change in the reporting month.
Future Key Issues
Key issues to be
considered in the next three months included:
Locations |
Site Activities |
Kai Tak |
·
Temporary working platform installation at underpass and
depressed road, ·
Base slab and wall construction at underpass, ·
Backfilling works at ventilation adit, ·
Excavation and ELS installation at cut & cover tunnel,
depressed road and underpass, ·
Temporary Grouting |
Ma Tau Kok |
·
TTM implementation, ·
Soft and rock excavation, ·
ELS installation for access shaft, ·
Pipe piling works for cut and cover tunnel, ·
Existing drainage diversion works, ·
Fresh water pipe installation works, ·
Precast segment installation and backfilling works at Landing
Step |
Kowloon Bay |
·
Wall tie installation and temporary reclamation for stage 1
temporary reclamation, ·
Excavation for stage 1 underwater tunnel, ·
S1, S2 Truss fabrication and installation, ·
Dewatering well and observation well installation, ·
Seawall Removal, ·
Temporary Grouting |
Barging Point |
·
Barging point operation (Spoil Disposal) |
·
Section 1:
Introduction
·
Section 2:
Project Information
·
Section 3:
Environmental Monitoring Requirement
·
Section 4:
Implementation Status of Environmental Mitigation Measures
·
Section 5:
Monitoring Results
·
Section 6:
Environmental Site Inspection and Audit
·
Section 7: Environmental Non-conformance
·
Section 8:
Future Key Issues
·
Section 9:
Conclusions and Recommendations
(a) construction of approximately 160m long cut-and-cover tunnel and
370m long underwater tunnel between the tunnel section at Ma Tau Kok and the depressed road of the CKR within Kai Tak
Development;
(b) reconstruction of the seawall at Ma Tau Kok
public pier, and the sloping seawall at the Former Kai Tak Airport Runway;
(c) construction of approximately 125m long depressed road and 200m
long underpass of the CKR within Kai Tak Development;
(d) construction of approximately 360m long underground tunnel
ventilation adit of the CKR;
(e) reconstruction of Kowloon City Ferry Pier Public Transport
Interchange; and
(f) other associated works.
Table 2.1 Construction Activities in the reporting month
Locations |
Site Activities |
Kai
Tak |
·
Construction of ventilation adit, ·
Construction of at-grade road and associated backfilling
works, ·
ELS removal at ventilation adit, ·
Excavation works at Underpass, ·
Construction of New Right of Way, ·
ELS installation works, ·
Temporary Grouting |
Ma
Tau Kok |
·
TTM implementation, ·
Soft Excavation and Rock Excavation, ·
Noise panel installation, ·
ELS installation & decking works for access shaft, ·
Construction of footpath, ·
Precast segment installation at Landing Step |
Kowloon
Bay |
·
Wall tie installation and temporary reclamation for stage 1
temporary reclamation, ·
Preparation work of K-frame tower and sliding system, ·
Excavation for stage 1 underwater tunnel, ·
Temporary Grouting, ·
Seawall Removal |
Barging
Point |
·
Barging point operation (Spoil
Disposal) |
Table 2.2 Contact Information of Key Personnel
Party |
Role |
Position |
Name |
Telephone |
Fax |
Arup-Mott
MacDonald Joint Venture |
Residential
Engineer (ER) |
Engineer’s
Representative |
Mr. Jeffrey
Lau |
2268 3640 |
2268 3954 |
ERM |
Independent
Environmental Checker (IEC) |
Independent
Environmental Checker |
Ms. Mandy To |
2271 3313 |
2723 5660 |
Gammon |
Contractor |
Contracts Manager |
Mr. Alan Yan |
2516 8823 |
2516 6260 |
Environmental Manager |
Ms Michelle Tang |
9267 8866 |
2516 6260 |
||
Environmental Officer |
Ms. Phoebe Ng |
9869 1105 |
|||
AECOM |
Contractor’s
Environmental Team (ET) |
ET Leader |
Mr. Y T Tang |
3922 9392 |
2317 7609 |
Table 2.3 Status of Environmental Licenses, Notifications and Permits
Permit / License No. / Notification/
Reference No. |
Valid Period |
Status |
Remarks |
|
From |
To |
|||
Further
Environmental Permit |
||||
FEP-01/457/2013/C |
28 Feb 2018 |
End of Project |
Valid |
-- |
Wastewater
Discharge License |
||||
WT00030290-2018 |
22 Mar 2018 |
31 May 2023 |
Valid |
Ma Tau Kok |
WT00030668-2018 |
27 Apr 2018 |
30 Apr 2023 |
Valid |
Site Office at
Kai Tak West |
WT00030358-2018 |
27 Apr 2018 |
30 Apr 2023 |
Valid |
Kai Tak West |
WT00030333-2018 |
27 Apr 2018 |
30 Apr 2023 |
Valid |
Barging Point
at Portions 4B & 4C |
WT00030330-2018 |
27 Apr 2018 |
30 Apr 2023 |
Valid |
Kowloon Bay |
Construction
Noise Permit |
||||
PP-RE0021-19 |
20 May 2019 |
15 Nov 2019 |
Valid |
Percussive Piling
at Stage 1 Temporary Reclamation Area |
GW-RE0632-19 |
27 Aug 2019 |
26 Feb 2020 |
Valid |
Barging Point
Operation at Kai Tak Barging Point |
GW-RE0740-19 |
20 Sep 2019 |
19 Dec 2019 |
Valid |
Welding, Pumping
Test and System at Ma Tau Kok |
GW-RS0524-19 |
5 July 2019 |
4 Jan 2020 |
Valid |
General Works
at Kai Tak |
GW-RE0779-19 |
2 Oct 2019 |
1 Jan 2020 |
Valid |
Welding and
backfilling at Stage 1 Underwater Tunnel |
Chemical Waste Producer Registration |
||||
5118-247-G2347-47 |
30 Jan 2018 |
End of Project |
Valid |
-- |
5118-247-G2347-48 |
30 Jan 2018 |
End of Project |
Valid |
-- |
Marine Dumping Permit |
||||
EP/MD/20-048 |
16 Oct 2019 |
15 Apr 2020 |
Valid on 16 Oct 2019 |
Sediments requiring Type 1 - Open Sea Disposal |
EP/MD/20-066 |
30 Sep 2019 |
29 Oct 2019 |
Valid until 29 Oct 2019 |
Sediments requiring Type 1 (Dedicated Site) and Type 2 Confined Marine
Disposal |
EP/MD/20-077 |
30 Oct 2019 |
29 Nov 2019 |
Valid on 30 Oct 2019 |
Sediments requiring Type 1 (Dedicated Site) and Type 2 Confined
Marine Disposal |
EP/MD/20-044 |
8 Oct 2019 |
7 Nov 2019 |
Valid on 8 Oct 2019 |
Sediments requiring Type 3 disposal (Filled up by 70%) |
Billing
Account for Construction Waste Disposal |
||||
7029909 |
22 Jan 2018 |
End of Project |
Account Active |
-- |
7031949 |
14 Oct 2019 |
14 Jan 2020 |
Account New on 14 Oct
2019 |
Billing Account for Disposal of
Construction Waste (by vessels) |
Notification Under
Air Pollution Control (Construction Dust) Regulation |
||||
429442 |
5 Jan 2018 |
5 Jul 2025 |
Notified |
-- |
Monitoring Requirements
Monitoring Equipment
Table 3.1 Air Quality Monitoring Equipment
Tisch
Total Suspended Particulate Mass Flow Controlled High Volume Air Sampler |
|
Portable
direct reading dust meter |
Sibata Digital Dust Monitor |
Monitoring Locations
Table 3.2 Location of Construction Dust Monitoring Station
Location |
Monitoring Station |
Description |
E-A14a
[1] |
Block
B of Merit Industrial Centre |
Rooftop
(13/F) |
[1] The air monitoring station
proposed in the EM&A Manual (i.e. Wyler Gardens with ID: E-A14) was not available
for impact dust monitoring, therefore impact monitoring was conducted at E-A14a
as an alternative which was agreed by the ER, IEC and EPD.
Monitoring
Methodology
(a)
The HVS
was installed in the vicinity of the air sensitive receivers. The following criteria were considered in the
installation of the HVS as far as practicable: -
(i)
A horizontal platform with
appropriate support to secure the sampler against gusty wind was provided.
(ii)
Two samplers should
not be placed less than 2m apart from each other;
(iii)
The distance between the HVS and
any obstacles, such as buildings, was at least twice the height that the
obstacle protrudes above the HVS.
(iv)
A minimum of 2 meters separation
from walls, parapets and penthouse for rooftop sampler.
(v)
A minimum of 2 meters separation
from any supporting structure, measured horizontally is required.
(vi)
No furnace or incinerator flues
nearby.
(vii)
Airflow around the sampler was
unrestricted.
(viii)
The sampler was located more than
20 meters from any dripline.
(ix)
Any wire fence and gate, required
to protect the sampler, did not obstruct the monitoring process.
(x)
Permission was obtained to set up
the samplers and access to the monitoring station.
(xi)
A secured supply of electricity
was obtained to operate the sampler.
(b)
Preparation
of Filter Papers
(i)
Glass fibre filters, G810 were
labelled and sufficient filters that were clean and
without pinholes were selected.
(ii)
All filters were equilibrated in
the conditioning environment for 24 hours before weighing. The conditioning
environment temperature was around 25 °C and not variable by more than ±3 °C;
the relative humidity (RH) was < 50% and not variable by more than ±5%. A
convenient working RH was 40%.
(iii)
All filter papers were prepared
and analysed by ALS Technichem (HK) Pty Ltd., which is a HOKLAS accredited
laboratory and has comprehensive quality assurance and
quality control programmes.
(c)
Field
Monitoring
(i)
The power
supply was checked to ensure the HVS works properly.
(ii)
The filter holder and the area
surrounding the filter were cleaned.
(iii)
The filter holder was removed by
loosening the four bolts and a new filter, with stamped number upward, on a
supporting screen was aligned carefully.
(iv)
The filter was properly aligned
on the screen so that the gasket formed an airtight seal on the outer edges of
the filter.
(v)
The swing bolts were fastened to
hold the filter holder down to the frame.
The pressure applied was sufficient to avoid
air leakage at the edges.
(vi)
Then the shelter lid was closed
and was secured with the aluminium strip.
(vii)
The HVS was warmed-up for about 5
minutes to establish run-temperature conditions.
(viii)
A new flow rate record sheet was
set into the flow recorder.
(ix)
On site temperature and
atmospheric pressure readings were taken and the flow rate of the HVS was
checked and adjusted at around 1.3 m3/min, and
complied with the range specified in the EM&A Manual (i.e. 0.6-1.7 m3/min).
(x)
The programmable digital timer
was set for a sampling period of 24 hrs, and the starting time, weather
condition and the filter number were recorded.
(xi)
The initial elapsed time was
recorded.
(xii)
At the end of sampling, on site
temperature and atmospheric pressure readings were taken and the final flow
rate of the HVS was checked and recorded.
(xiii)
The final elapsed time was
recorded.
(xiv)
The sampled filter was removed
carefully and folded in half length so that only
surfaces with collected particulate matter were in contact.
(xv)
It was then placed in a clean
envelope and sealed.
(xvi)
All monitoring information was
recorded on a standard data sheet.
(xvii) Filters were then sent to ALS Technichem (HK) Pty Ltd. for analysis.
(d)
Maintenance
and Calibration
(i)
The HVS and its accessories were maintained in good working condition, such as
replacing motor brushes routinely and checking electrical wiring to ensure a
continuous power supply.
(ii)
HVSs were calibrated using
TE-5025A Calibration Kit upon installation and thereafter at bi-monthly
intervals.
(iii)
Calibration certificate of the TE-5025A Calibration Kit and the HVSs are provided in
Appendix E.
(a)
Measuring Procedures
The measuring procedures of the 1-hour dust
meter are in accordance with the Manufacturer’s Instruction Manual as follows:
(i)
Turn the power on.
(ii)
Close the air collecting opening cover.
(iii)
Push the “TIME SETTING” switch to [BG]
(iv)
Push “START/STOP”
switch to perform background measurement for 6 seconds.
(v)
Turn the knob at SENSI ADJ position to insert
the light scattering plate.
(vi)
Leave the equipment for 1 minute upon “SPAN
CHECK” is indicated in the display.
(vii)
Push “START/STOP” switch to perform automatic
sensitivity adjustment. This measurement takes 1 minute.
(viii)
Pull out the knob and return it to MEASURE
position.
(ix)
Push the “TIME SETTING” switch the time set
in the display to 3 hours.
(x)
Lower down the air collection opening cover.
(xi)
Push “START/STOP” switch to start
measurement.
(b)
Maintenance and
Calibration
(i)
The 1-hour TSP meter
was calibrated at 1-year intervals against a continuous particulate TEOM
Monitor, Series 1400ab. Calibration certificates of the Laser Dust Monitors are
provided in Appendix E.
Monitoring Schedule for the
Reporting Month
Monitoring Requirements
Table 3.3 Noise Monitoring Parameters, Frequency and Duration
Parameter and Duration |
Frequency |
30-mins
measurement at each monitoring station between 0700 and 1900 on normal
weekdays. Leq, L10 and L90
would be recorded. |
At least once per week |
Table 3.4 Noise Monitoring Equipment for Regular Noise Monitoring
B&K (Model No. 2238) |
|
Acoustic
Calibrator |
B&K (Model
No. 4231) |
Monitoring Locations
Table 3.5 Noise Monitoring Stations during Construction Phase
Location |
Monitoring Station |
Description |
Measurement |
E-N12a [1] |
19 Hing Yan Street |
Rooftop (9/F) |
Façade |
E-N21a [1] |
Block B of Merit Industrial Centre |
Rooftop (13/F) |
Free field [2] |
Notes:
[1] The noise monitoring stations proposed in
the EM&A Manual (i.e. Grand Waterfront Tower 3 with ID: E-N12 and Hang Chien Court Block J with ID: E-N21) were not available for
impact noise monitoring, therefore impact monitoring was conducted at E-N12a
and E-N21a as an alternative which was
agreed by the ER, IEC and EPD.
[2] A
correction of +3 dB(A) was made to the free field measurements.
Monitoring
Parameters, Frequency and Duration
Table 3.6 Noise Monitoring Parameters, Frequency and Duration
Location |
Parameter and Duration |
Frequency |
E-N12a and E-N21a |
30-mins measurement at each
monitoring station between 0700 and 1900 on normal weekdays. Leq, L10 and L90 would
be recorded. |
At
least once per week |
Monitoring Methodology
(a)
The sound level meter was set on
a tripod at a height of 1.2 m above the ground.
(b)
Façade measurement was made at
E-N12a.
(c)
Free field measurements was made at monitoring location E-N21a. A correction of +3
dB(A) shall be made to the free field measurements.
(d)
The battery condition was checked to ensure the correct
functioning of the meter.
(e)
Parameters such as frequency
weighting, the time weighting and the measurement time were set as follows:
(i)
frequency weighting: A
(ii)
time weighting: Fast
(iii)
time measurement: Leq(30-minutes) during non-restricted
hours i.e. 0700 – 1900 on normal weekdays.
(f)
Prior to and after each noise
measurement, the meter was calibrated using the acoustic calibrator for 94
dB(A) at 1000 Hz. If the difference in
the calibration level before and after measurement was more than 1 dB(A), the
measurement would be considered invalid and repeat of noise measurement would
be required after re-calibration or repair of the equipment.
(g)
During the monitoring period, the
Leq, L10 and L90
were recorded. In addition, site
conditions and noise sources were recorded on a standard record sheet.
(h)
Noise measurement was paused
during periods of high intrusive noise (e.g. dog barking, helicopter noise) if
possible. Observations were recorded when intrusive noise was unavoidable.
(i)
Noise monitoring was cancelled in
the presence of fog, rain, wind with a steady speed exceeding 5m/s, or wind
with gusts exceeding 10m/s.
(a)
The
microphone head of the sound level meter was cleaned with soft
cloth at regular intervals.
(b)
The meter
and calibrator were sent to the supplier or HOKLAS laboratory to check and
calibrate at yearly intervals.
(c)
Calibration
certificates of the sound level meters and acoustic calibrators are
provided in Appendix
E.
Monitoring Schedule for the
Reporting Month
Table 4.1 Status of Required Submission under Environmental Permit
EP Condition |
Submission |
Submission
Date |
Condition 3.4 of |
Monthly EM&A Report for
September 2019 |
14 October 2019 |
Table 5.1 Summary of 24-hour
TSP Monitoring Result in the Reporting Period
ID |
Average (mg/m3) |
Range (mg/m3) |
Action Level (mg/m3) |
Limit Level (mg/m3) |
E-A14a |
44.5 |
15.0 – 66.9 |
197.3 |
260 |
Table 5.2 Summary of 1-hour TSP Monitoring Result in the Reporting Period
ID |
Average (mg/m3) |
Range (mg/m3) |
Action Level (mg/m3) |
Limit Level (mg/m3) |
E-A14a |
64.4 |
60.6 – 68.5 |
302.4 |
500 |
Table 5.3 Summary of Construction Noise Monitoring Results in the Reporting Period
ID |
Range, dB(A), Leq (30 mins) |
Limit Level, dB(A), Leq (30 mins) |
E-N12a |
64.7
– 68.6 |
75 |
E-N21a |
63.4
– 67.2 |
75 |
l Excavation profiles
must be properly designed and executed.
l Stockpiling site(s) shall
be lined with impermeable sheeting and bunded. Stockpiles shall be fully
covered by impermeable sheeting to reduce dust emission.
l Excavation and
stockpiling should be carried out during dry season as far as possible to
minimise potentially contaminated runoffs from the Concerned Soil.
l Regular site audit
will be conducted under the Environmental Monitoring and Audit (EM&A)
programme to ensure the soil excavation, stockpiling and backfilling works are
carried out in accordance with this report.
Findings of the site audit will be presented in Table 6.1.
l The truck
transferring Concerned Soil shall be covered entirely by impervious sheeting to
ensure that the dusty materials do not leak from the truck.
Table 6.1 Observations and
Recommendations of Site Audit
Parameters |
Date |
Observations and Recommendations |
Follow-up |
Air
Quality |
2 October 2019 |
· Dust emission
was observed during the loading and unloading activities at Kai Tak. The Contractor
was reminded to provide water spraying for dusty material. |
The item was
rectified by the Contractor on 3 Oct 2019. |
9 October 2019 |
· NRMM label was
not observed on drill rig at Ma Tau Kok. The
Contractor was reminded to affix the proper NRMM on drill rig. |
The item was
rectified by the Contractor on 14 Oct 2019. |
|
23 October 2019 |
Reminder: · The Contractor
was reminded to spray the water regularly on the exposed area at Ma Tau Kok to avoid the dust emission from the machinery
movement. |
The item was rectified
by the Contractor on 24 Oct 2019. |
|
Noise |
2 October 2019 |
·
Breaker head was
observed without proper wrapping of acoustic material during the breaking at
Ma Tau Kok. The Contractor was reminded to wrap the
breaker head with acoustic material to minimize the noise impact. |
The item was
rectified by the Contractor on 4 Oct 2019. |
9 October 2019 |
Reminder: ·
The Contractor was reminded to wrap the breaker
head with the acoustic material before commencing the breaking activity at Ma
Tau Kok Access Shaft. |
The item was
rectified by the Contractor on 10 Oct 2019. |
|
Water
Quality |
2 October 2019 |
· Gaps of silt
curtain were observed at steel platform. The Contractor was reminded to seal
the gap of silt curtain to ensure the enclosure for marine works. |
The item was
rectified by the Contractor on 8 Oct 2019. |
9 October 2019 |
· Chemical
containers were observed stored without drip tray at Ma Tau Kok Access Shaft. The Contractor was reminded to provide
a drip tray for the prevention of chemical spillage. |
The item was
rectified by the Contractor on 11 Oct 2019. |
|
16 October 2019 |
· Stagnant water
was accumulated inside the drip tray of oil containers at Kai Tak. The
Contractor was reminded to remove the stagnant water which inside the drip
tray for oil spillage prevention. |
The item was
rectified by the Contractor on 18 Oct 2019. |
|
23 October 2019 |
Reminder: · The Contractor
was reminded to seal the gap of silt curtain at Steel platform. |
The item will
be followed up in next reporting period. |
|
Waste/
Chemical Management |
2 October 2019 |
· General refuse
was observed accumulated at the worker’s area of Landing Step Area. The Contractor was reminded to remove the
general refuse regularly. |
The item was
rectified by the Contractor on 8 Oct 2019. |
31 October 2019 |
· Chemical waste
containers stored without drip tray was observed at Ma Tau Kok. The Contractor was advised to store chemical waste
containers with drip tray to prevent leakage of chemical waste. |
The item will
be followed up in next reporting period. |
|
Land
Contamination |
Nil |
Nil |
Nil |
Landscape &
Visual |
Nil |
Nil |
Nil |
Permits/ Licenses |
Nil |
Nil |
Nil |
Table 7.1 Construction Activities in the coming three months
Locations |
Site Activities |
Kai
Tak |
·
Temporary working platform installation at underpass and
depressed road, ·
Base slab and wall construction at underpass, ·
Backfilling works at ventilation adit, ·
Excavation and ELS installation at cut & cover tunnel,
depressed road and underpass, ·
Temporary Grouting |
Ma
Tau Kok |
·
TTM implementation, ·
Soft and rock excavation, ·
ELS installation for access shaft, ·
Pipe piling works for cut and cover tunnel, ·
Existing drainage diversion works, ·
Fresh water pipe installation works, ·
Precast segment installation and backfilling works at
Landing Step |
Kowloon
Bay |
·
Wall tie installation and temporary reclamation for stage 1
temporary reclamation, ·
Excavation for stage 1 underwater tunnel, ·
S1, S2 Truss fabrication and installation, ·
Dewatering well and observation well installation, ·
Seawall Removal, ·
Temporary Grouting |
Barging
Point |
·
Barging point operation (Spoil
Disposal) |